Project Budget Template: A Worked Example, and the Column Most Budgets Are Missing
Quick answer: A project budget lists every cost your project will incur, grouped by category, with a contingency reserve on top. Build it from the bottom up: estimate each line item, add the subtotals to get your base cost, add contingency to get your cost baseline, then add management reserve for the total budget.
Most budget templates give you three columns: Budget, Actual, Variance.
Those three columns will tell you that you’re fine, right up until the invoices land. Then you discover that the money was gone two months ago — you just hadn’t been billed yet.
This guide gives you a complete worked budget with every number adding up, and a fourth column that fixes the problem. In the example below, “Actual” says you’ve spent 46.5% of the budget. The fourth column says 70.3% is already gone.
Table of Contents
What Is a Project Budget?
A project budget is the total money approved for a project, broken down into the costs that make it up.
A project budget plan does two jobs, and they’re different:
| Job | What it means | When it matters |
|---|---|---|
| Authorising | Getting the money approved | Before the project starts |
| Controlling | Checking spend against plan | Every week after that |
Most budget problems come from doing the first job well and the second badly. A beautiful spreadsheet approved in January tells you nothing in June unless somebody is updating it.
What a project budget is not
| Not the same as | Difference |
|---|---|
| A cost estimate | An estimate is your calculation. A budget is the approved money |
| A quote | A quote is one supplier’s price for one piece of work |
| A cash flow forecast | A budget says how much. Cash flow says when it leaves the bank |
| A business case | The business case justifies the spend. The budget plans it |
That third one catches people out. You can be perfectly on budget and still run out of cash, because the money was all due in month two. A budget with a timing column is a budget you can actually fund.
What’s the Difference Between a Cost Estimate, a Cost Baseline, and a Project Budget?
These three terms get used interchangeably, and they mean three different amounts of money. Getting them straight is the most useful ten minutes you’ll spend on this subject.
| Term | What it is | Who controls it |
|---|---|---|
| Base cost estimate | The sum of your line items, with no buffer | Project manager |
| + Contingency reserve | A buffer for risks you identified | Project manager |
| = Cost baseline | What you measure performance against | Project manager |
| + Management reserve | A buffer for things nobody saw coming | Sponsor |
| = Total project budget | The whole authorised amount | Sponsor |
The stack, in order
Line items added up → BASE COST ESTIMATE
+ contingency reserve → COST BASELINE
+ management reserve → TOTAL PROJECT BUDGET
Why the layers matter
You’re measured against the cost baseline, not the total budget. That’s the number that matters when someone asks “are we over budget?”
You can spend contingency yourself. It’s yours, set aside for risks you already wrote down. Using it isn’t failure — it’s the reserve doing its job.
You cannot touch management reserve. It sits above your baseline and belongs to the sponsor. Reaching for it means going back and asking, which is a different conversation entirely.
This is why “are we on budget?” is a sloppy question. The honest answer is usually two numbers: where you are against baseline, and how much contingency you’ve used. The worked example below shows a project that is under baseline and has used nearly half its contingency at the same time. Both are true. They feel completely different.
What Should a Project Budget Include?
How to create a project budget starts here: work through these seven categories. Most forgotten costs live in the bottom three.
| Category | Examples | Commonly forgotten |
|---|---|---|
| Internal labour | Your own team’s days × day rate | People often leave this out entirely |
| External services | Consultants, contractors, agencies | Travel and expenses on top of day rates |
| Software and licences | Subscriptions, seats, integration tools | Year-one cost vs ongoing; extra seats |
| Hardware and equipment | Devices, servers, kit | Delivery, setup, disposal of the old kit |
| Training and change | Trainers, materials, backfill cover | The time learners spend away from their job |
| Travel and facilities | Trips, room hire, shipping | Currency moves on overseas suppliers |
| Contingency and reserve | Risk buffer | Treated as padding instead of a plan |
The five costs people forget most often
- Your own team’s time. It feels free because the salaries are already paid. It isn’t free — it’s the largest line in most projects, and leaving it out makes the project look cheaper than it is.
- The cost of people being trained. Forty staff away from their desks for a day is a real cost, even if no invoice appears.
- Year two. A licence bought in month nine renews in month twenty-one. State clearly whether your budget covers year one only.
- Decommissioning the old thing. Data extraction, contract exit fees, disposal.
- Your own time managing it. The project manager is a project cost.
What Does a Completed Project Budget Example Look Like?
Here’s a full budget for a CRM implementation. Every line, every subtotal, every total.
Internal labour
| Line item | Calculation | Cost |
|---|---|---|
| Project manager | 60 days × $400 | $24,000 |
| Business analyst | 40 days × $350 | $14,000 |
| IT lead | 25 days × $450 | $11,250 |
| Subtotal | $49,250 |
External services
| Line item | Calculation | Cost |
|---|---|---|
| Implementation partner | Fixed fee | $38,000 |
| Data migration specialist | 15 days × $600 | $9,000 |
| Subtotal | $47,000 |
Software and licences
| Line item | Calculation | Cost |
|---|---|---|
| CRM licences, year 1 | 45 users × $85 × 12 months | $45,900 |
| Integration middleware | Annual | $6,200 |
| Subtotal | $52,100 |
Hardware
| Line item | Calculation | Cost |
|---|---|---|
| Tablets for field team | 12 × $540 | $6,480 |
| Subtotal | $6,480 |
Training
| Line item | Calculation | Cost |
|---|---|---|
| Trainer | 6 days × $700 | $4,200 |
| Materials and room hire | $1,800 | |
| Subtotal | $6,000 |
Travel
| Line item | Calculation | Cost |
|---|---|---|
| Site visits | 8 trips × $320 | $2,560 |
| Subtotal | $2,560 |
Putting it together
| Category | Subtotal |
|---|---|
| Internal labour | $49,250 |
| External services | $47,000 |
| Software and licences | $52,100 |
| Hardware | $6,480 |
| Training | $6,000 |
| Travel | $2,560 |
| Base cost estimate | $163,390 |
| Contingency reserve (10% of base) | $16,339 |
| Cost baseline | $179,729 |
| Management reserve (5% of baseline) | $8,986 |
| Total project budget | $188,715 |
Check the arithmetic yourself
Every budget should survive three checks. This one does:
- Subtotals add to the base. 49,250 + 47,000 + 52,100 + 6,480 + 6,000 + 2,560 = 163,390 ✓
- Base + contingency = baseline. 163,390 + 16,339 = 179,729 ✓
- Baseline + management reserve = total. 179,729 + 8,986 = 188,715 ✓
A note on untidy numbers. $163,390 isn’t a round figure, and neither is $16,339. That’s what a real budget looks like when you build it from line items rather than working backwards from a number someone already had in mind. If your budget comes out at exactly $150,000, check whether you estimated it or just agreed to it.
How Do You Estimate Costs?
Five methods. Most projects use three of them in the same budget, which is fine — different lines need different approaches.
| Method | How it works | Accuracy | Use when |
|---|---|---|---|
| Expert judgement | Ask someone who’s done it | Varies wildly | You have a genuine expert and little data |
| Analogous | “The last one cost $140k, this is bigger, so $180k” | −25% to +75% | Very early, or for a rough order of magnitude |
| Parametric | Cost per unit × number of units | −15% to +25% | The work scales with something countable |
| Bottom-up | Estimate every line, add them up | −5% to +15% | You know the scope. This is the one to aim for |
| Three-point | Combine best, likely and worst cases | Depends on inputs | A line item is genuinely uncertain |
How to pick
Bottom-up is the target. The example above is bottom-up — 45 users at $85, 60 days at $400. It takes longest and it’s by far the most defensible, because every number traces to something.
Analogous is for the first conversation only. It’s fast and it’s wide. The range on an analogous estimate is roughly minus a quarter to plus three quarters, which is a way of saying you don’t know yet. Never present one as a budget.
Parametric is the quiet winner. Where work scales with a countable thing — users, square metres, pages, records — cost per unit times quantity is quick and surprisingly accurate. The CRM licence line is parametric.
Three-point is for the scary lines. You don’t need it for everything, only for the handful you’re genuinely unsure about.
The rule that matters more than the method
Ask the person who’ll do the work. An estimate you invented at your desk is a guess with a dollar sign on it. Ask for a range rather than a single number, and ask what would have to be true for the optimistic end to happen.
When the work is going out to suppliers, a request for proposal is how you turn guesses into priced quotes. Three real quotes beat any estimating technique.
How Do You Use a Three-Point Estimate?
Three-point estimating takes your uncertainty and turns it into a single number you can put in a budget.
You need three figures for the task:
- O — Optimistic: everything goes right
- M — Most likely: the realistic case
- P — Pessimistic: it goes badly, but not catastrophically
The formula
Expected cost or duration = (O + 4M + P) / 6
The most likely case is weighted four times, because it’s the most probable. The two extremes pull the answer slightly in their direction.
A worked example
Take the data migration from the budget above. Ask the specialist for three numbers:
| Days | |
|---|---|
| Optimistic (clean data, no surprises) | 8 |
| Most likely | 15 |
| Pessimistic (duplicate records, bad formats) | 34 |
Three-point estimate: (8 + 4 × 15 + 34) ÷ 6 = (8 + 60 + 34) ÷ 6 = 102 ÷ 6 = 17 days
Compare it to a simple average: (8 + 15 + 34) ÷ 3 = 57 ÷ 3 = 19 days
The simple average gives 19 days. The weighted formula gives 17. The weighting is what stops one alarming worst case from dragging your whole estimate upward.
What this tells you about the budget
The budget above used 15 days — the most likely figure — at $600 a day, so $9,000.
The three-point estimate says 17 days, which is $10,200. That’s $1,200 more than the budget line.
This is exactly what contingency is for. You don’t inflate the line to $10,200 and hide the buffer inside it. You budget the realistic figure, and you hold the difference centrally where you can see it and manage it.
The spread tells you how worried to be
Rough standard deviation = (P − O) / 6
Here: (34 − 8) ÷ 6 = 26 ÷ 6 = 4.33 days.
A spread of 4.33 days on a 17-day estimate is wide — roughly a quarter of the task. That’s a signal to look harder at the data quality before you commit to a date, not just to add money.
A useful habit: when the pessimistic figure is more than three times the optimistic one, stop estimating and go find out more. A range that wide means you don’t understand the task yet, and no formula fixes that.
How Much Contingency Should You Add?
| Project type | Typical contingency | Why |
|---|---|---|
| Repeat work you’ve done many times | 5% | Few unknowns |
| Standard project, known approach | 10% | The usual starting point |
| New technology or new supplier | 15–20% | More can surprise you |
| Research, R&D, first-of-a-kind | 25%+ | Genuinely unpredictable |
| Fixed-price contract you’re delivering | Higher — the risk is yours | You absorb overruns |
These are starting points, not answers.
The better way to size it
A flat percentage is a guess dressed up as a method. Sizing it from your actual risks is more work and much more defensible:
| Risk | If it happens, it costs | Chance | Expected value |
|---|---|---|---|
| Data worse than expected | $8,000 | 50% | $4,000 |
| Extra licences needed | $6,000 | 30% | $1,800 |
| Partner delay extends PM time | $10,000 | 40% | $4,000 |
| Hardware price rise | $1,500 | 60% | $900 |
| Total | $10,700 |
Multiply each cost by its probability, add them up. That total is your evidence-based contingency figure.
The $16,339 in the example above is 10% of base. That’s more than this risk analysis suggests, which is defensible on a project with a new supplier. What matters is that you can explain the number. “It’s 10%” is an answer nobody can argue with or learn from. “It’s these four risks plus a margin for the new partner” is a number you can defend in a steering meeting.
Your contingency plan is where the responses to those risks get written down.
Three rules for contingency
- Hold it centrally. One contingency line, not padding hidden in every estimate. Hidden padding gets spent without anyone deciding to spend it.
- Require a decision to release it. Even if that decision is just you writing a line in the log.
- Log every release. What it was for, how much, what’s left. This log is the single most useful document when someone asks where the money went.
What’s the Difference Between Contingency and Management Reserve?
| Contingency reserve | Management reserve | |
|---|---|---|
| Covers | Risks you identified | Things nobody foresaw |
| Sits | Inside the cost baseline | Outside the baseline |
| Controlled by | Project manager | Sponsor |
| To use it | Your decision, logged | Formal request to the sponsor |
| Typical size | 5–25% of base cost | 5–10% of baseline |
| In the example | $16,339 | $8,986 |
The practical difference
Contingency is for the known unknowns. You wrote the risk down, you costed it, it happened. You release the money and log it. No meeting needed.
Management reserve is for the unknown unknowns. A regulation changes. A supplier goes bust. The thing nobody had on the list. Getting at it means going back to the sponsor and explaining, which is appropriate — a surprise that big deserves a conversation.
Why the baseline boundary matters
Spending contingency does not make you over budget. It’s inside your baseline; that’s what it’s there for.
Touching management reserve does change the authorised amount. Your baseline gets reset, and reported performance restarts from the new number.
That’s the whole reason for the boundary. One pot absorbs the risks you planned for, quietly. The other one makes a noise, because something happened that nobody planned for at all.
What Goes in the Project Budget Template?
Copy this. The Committed column is the one most templates leave out, and the next section explains why it matters.
PROJECT BUDGET
Project:
Version: Date:
Prepared by: Approved by:
Currency: Covers: Year 1 only / full life
LINE ITEMS
| Cat | Line item | Basis of estimate | Qty | Rate | Budget | Month due |
| | | | | | | |
SUMMARY
| Category | Budget |
| Internal labour | |
| External services | |
| Software and licences | |
| Hardware | |
| Training and change | |
| Travel and facilities | |
| BASE COST ESTIMATE | |
| Contingency reserve | |
| COST BASELINE | |
| Management reserve | |
| TOTAL PROJECT BUDGET | |
TRACKING
| Category | Budget | Actual | Committed | Remaining | Forecast |
Remaining = Budget − Actual − Committed
CONTINGENCY LOG
| Date | Released for | Amount | Approved by | Balance left |
ASSUMPTIONS
1. Day rates as at [date]; rises after [date] not included
2. Covers year 1 licences only
3. Internal labour at [rate]; excludes recruitment
4. Excludes [named exclusions]
5. Currency: [X]; no allowance for exchange movement
CHECKS
[ ] Subtotals add to the base cost estimate
[ ] Base + contingency = cost baseline
[ ] Baseline + management reserve = total budget
[ ] Actual + Committed + Remaining = Budget, every row
[ ] Every line has a basis of estimate
[ ] Internal labour is included
[ ] Someone named has approved it
The “basis of estimate” column is the one to protect. In six months, nobody will remember why the training line was $6,000. A column saying “trainer quote 14 Oct, 6 days” answers that in five seconds, and it’s the difference between a budget you can defend and one you have to rebuild.
Why Do You Need a Committed Cost Column?
This is the fix for the most common way budgets fail, and almost no template has it.
The three kinds of “spent”
| Status | Meaning | On your bank statement? |
|---|---|---|
| Actual | Invoiced and paid | Yes |
| Committed | Contract signed or PO raised, not yet invoiced | No — not yet |
| Remaining | Not yet promised to anyone | No |
Committed money is gone. You signed for it. But it hasn’t been invoiced, so it doesn’t show in Actual — and a three-column budget shows you nothing but Actual.
Remaining = Budget − Actual − Committed
What it looks like in practice
Here’s the CRM project at month four.
| Category | Budget | Actual | Committed | Remaining |
|---|---|---|---|---|
| Internal labour | $49,250 | $22,000 | $0 | $27,250 |
| External services | $47,000 | $19,000 | $28,000 | $0 |
| Software and licences | $52,100 | $45,900 | $6,200 | $0 |
| Hardware | $6,480 | $0 | $6,480 | $0 |
| Training | $6,000 | $0 | $4,200 | $1,800 |
| Travel | $2,560 | $900 | $0 | $1,660 |
| Contingency reserve | $16,339 | $0 | $0 | $16,339 |
| Management reserve | $8,986 | $0 | $0 | $8,986 |
| Total | $188,715 | $87,800 | $44,880 | $56,035 |
Check it: 87,800 + 44,880 + 56,035 = 188,715 ✓ — the three columns must always add back to the budget.
The number that changes the conversation
| Measure | Amount | % of total budget |
|---|---|---|
| Actual spend only | $87,800 | 46.5% |
| Actual + committed | $132,680 | 70.3% |
A three-column budget would report 46.5% at month four and everyone would relax.
The truth is that 70.3% of the money is already gone. Against the base cost estimate of $163,390 — the part that isn’t reserve — it’s 81.2%.
Look at the rows to see how it happens. External services shows $19,000 actual against a $47,000 budget, which looks like plenty of room. But $28,000 is committed, so Remaining is zero. That line is fully spent and the Actual column won’t admit it for another two months.
Hardware is the starkest: $0 actual, $6,480 committed, nothing left. The tablets are ordered. A three-column budget calls that line untouched.
Where to get the committed figure
| Source | What to pull |
|---|---|
| Purchase order system | Open POs not yet invoiced |
| Signed contracts | Total value minus what’s been billed |
| Finance team | Accruals and commitments, usually monthly |
| Your own records | Anything you’ve emailed “yes, go ahead” about |
That last row is where the leaks are. An email saying “yes, please proceed” is a commitment even if no PO exists. If you’ve told a supplier to start, the money is committed.
One warning
Don’t double-count. When an invoice arrives, the amount moves from Committed to Actual. It doesn’t appear in both. The check that catches this is the one above — if your three columns stop adding up to Budget, something has been counted twice.
How Do You Forecast the Final Cost?
Forecasting is one sum, done honestly.
Forecast at completion = Actual + Committed + Estimate of work not yet committed
Worked on the CRM project
At month four, the team estimates $38,500 of work still to be ordered.
| Component | Amount |
|---|---|
| Actual spend | $87,800 |
| Committed | $44,880 |
| Estimate for the rest | $38,500 |
| Forecast at completion | $171,180 |
Now read it against both benchmarks
| Compared with | Amount | Result |
|---|---|---|
| Cost baseline | $179,729 | $8,549 under |
| Base cost estimate | $163,390 | $7,790 over |
Both are true, and they sound like opposite news.
You are forecasting under baseline. Good. There’s $8,549 of headroom.
But you’ve consumed $7,790 of contingency — that’s 47.7% of the $16,339 you set aside — and you’re four months into the project.
That second sentence is the one to say out loud in a steering meeting. The headline number looks fine. The contingency burn rate says you’ll be out of buffer before you’re out of project. That’s the thing to act on now, while there’s still something to act with.
The simplest early-warning check
| Check | How |
|---|---|
| Contingency burn | % of contingency used vs % of project elapsed |
| Committed share | Actual + Committed as a % of budget vs % elapsed |
| Zero-remaining rows | Any category where Remaining hit $0 early |
The contingency burn check is the single most useful one. If you’re 25% through the project and 48% through your contingency, you have a problem that no other number on the page is showing you.
For how this fits into regular reporting, see the project control process and the project performance evaluation plan.
What Are the Most Common Project Budget Mistakes?
- Leaving out internal labour. The largest cost on most projects, left out because no invoice arrives for it.
- No Committed column. Covered above. You find out two months late, every time.
- Padding every line instead of holding central contingency. Hidden buffer gets spent without a decision.
- Working backwards from a number. Somebody says “we’ve got about $150k” and the estimate is reverse-engineered to fit. The arithmetic looks fine and means nothing.
- No basis of estimate. In six months nobody can defend any line, so the whole budget gets rebuilt.
- No assumptions list. Then the argument about whether year two was included happens at the worst possible moment.
- Forgetting the cost of change. Training, backfill, the productivity dip after go-live.
- Never updating it. A budget that isn’t maintained is a historical document.
- Confusing contingency with management reserve. Spending the sponsor’s reserve without asking is a quick way to lose their trust.
- One currency, several countries. An overseas supplier’s price moves even when nothing about your project does.
How Do You Ask for More Money?
It happens on good projects too. How you ask decides how it goes.
| Do | Don’t |
|---|---|
| Ask as soon as you know | Wait until you’ve already overspent |
| Bring one number, with the breakdown behind it | Bring a range and ask them to pick |
| Explain what changed since approval | Explain that estimating is hard |
| Show what you’ve already absorbed | Imply nothing could have been done |
| Offer options, including a reduced-scope one | Present it as pay-or-fail |
| Say what it buys | Say what it avoids |
The structure that works
1. What changed. One or two sentences, factual. “The data was in worse shape than the sample suggested. Migration is 17 days, not 15.”
2. What you did about it. “We absorbed the first $7,790 from contingency and re-sequenced the training to save $1,400.”
3. What you need. One number, with the breakdown attached.
4. What happens if you don’t get it. Specific and undramatic. Which deliverable moves, by how long.
5. The options. Usually three: full scope at the new number, reduced scope at the old number, or delay the remainder to next year’s budget.
The thing that decides the answer
Whether you flagged it early. A sponsor asked for more money in month four, with the arithmetic shown and options offered, usually says yes. The same sponsor told in month nine that the money ran out in month seven says no — and stops trusting the numbers after that.
Bad news travels badly when it travels late. The contingency burn check above is how you spot it in time to be the one who raises it.
What Tools Can You Build a Project Budget In?
| Tool type | Good for | Watch out for |
|---|---|---|
| Spreadsheets | Nearly everything. Full control, easy checks | No audit trail unless you add one; broken formulas are invisible |
| Project management platforms | Linking costs to tasks and resources | Often no Committed field — you may have to add a custom one |
| Finance and ERP systems | Real actuals and real PO data | Reports by cost code, not by your categories |
| Dedicated cost tools | Large capital programmes | Overkill under a few hundred thousand |
Features worth more than the brand:
- A Committed field. If the tool only has Budget and Actual, you’ll be keeping the real picture in a spreadsheet anyway.
- Access to PO data. Ideally from the system that raises them, not retyped.
- A contingency log. Separate from the budget lines.
- Version history. So “what did we approve in January?” has an answer.
For most projects, a spreadsheet plus a monthly extract of open POs from finance beats any single tool. The spreadsheet gives you the structure in this guide; finance gives you the committed figures you can’t see yourself. Our project management tools page covers the wider set.
One habit worth more than any tool: reconcile against finance monthly. Your Actual column and their ledger will disagree. The disagreement is always informative, and it’s usually an invoice you didn’t know about.
How Does Writegenic AI Fit In?
A budget spreadsheet doesn’t explain itself, and the writing around it is what gets it approved.
Writegenic AI can help you:
- Write the basis of estimate for each line, so the numbers stay defensible
- Draft the assumptions and exclusions list — the section that prevents arguments later
- Turn the budget into a one-page summary for the people who won’t open the file
- Write the monthly budget update, including the contingency burn position
- Draft the request for more money using the five-part structure above
- Write the contingency release note when you draw on the reserve
It also helps with the documents around it. The project charter the budget is approved against. The project scope that decides what’s in it. And the contingency plan behind the reserve.
Explore AI for project management or sharpen your instructions with the prompt generator.
Draft with the tool, keep the judgement. AI can lay out a budget, write the assumptions and draft the update email in minutes. It cannot tell you that your implementation partner always bills at the top of their range, that your finance team closes the month three days late so your actuals are always stale, or that this sponsor needs bad news on a Tuesday and in person. Those three things will decide how your budget actually goes, and none of them is in the spreadsheet.
Frequently Asked Questions
What is a project budget?
The total money approved for a project, broken into the costs that make it up. It authorises the spend before the project starts, and gives you something to control spending against afterwards.
What should a project budget include?
Internal labour, external services, software and licences, hardware, training and change, travel and facilities, and a contingency reserve. Internal labour is the one most often left out and usually the largest.
What is the difference between a cost baseline and a project budget?
The cost baseline is your base estimate plus contingency reserve — the number your performance is measured against. The total project budget adds management reserve on top, which the sponsor controls.
How much contingency should a project budget have?
10% of base cost is the usual starting point. Use 5% for repeat work, 15–20% for new technology or a new supplier, and 25% or more for genuinely novel work. Better still, size it from your actual costed risks.
What is the three-point estimate formula?
(Optimistic + 4 × Most likely + Pessimistic) ÷ 6. For 8, 15 and 34 days that gives (8 + 60 + 34) ÷ 6 = 17 days. The most likely figure is weighted four times.
What is the difference between contingency reserve and management reserve?
Contingency covers risks you identified and sits inside the baseline, controlled by you. Management reserve covers surprises nobody foresaw, sits outside the baseline, and needs the sponsor’s approval to release.
Does using contingency mean you’re over budget?
No. Contingency is inside your cost baseline, so spending it is the reserve doing its job. You’re over budget when you need management reserve, which resets the authorised amount.
What is a committed cost?
Money you’ve contractually promised — a signed contract or raised purchase order — that hasn’t been invoiced yet. It’s gone, but it won’t appear in your Actual column, which is why budgets need a separate Committed column.
How do you calculate remaining budget?
Remaining = Budget − Actual − Committed. If you subtract only Actual, you’ll overstate what’s left by the whole value of your open orders.
How do you forecast the final project cost?
Actual spend, plus committed costs, plus an estimate of work not yet committed. Then compare it against your cost baseline and your base cost estimate. Those two give different answers, and you need both.
How do you know if a project budget is in trouble early?
Compare the percentage of contingency used against the percentage of the project elapsed. Say you’re 25% through the work and 48% through the contingency. That’s a warning no other number on the page will show you.
Can AI create a project budget?
It can draft the structure, write the basis of estimate for each line, and produce the summary and update emails. The rates, quantities and quotes have to come from suppliers and from the people doing the work.